Installation and maintenance
Storage: every component must be stored in a dry place, safe from bumps and dust.
Slabs: the slab must be solid, with a smooth, regular surface. Slabs and plaster must have reached the right degree of maturity (at least one month old). We recommend to apply a coat of anti-dust sealant to the slab.
Finish and installation: technological and electrical systems, false ceilings, anti-dust treatment, painting, and the installation of doors and windows, glass, sills and steps must be completed before the raised floor is installed.
Environmental conditions: no particular precautions are necessary.
Moving loads: always use lift trucks and rigid board when moving heavy structures (cupboards, machinery, etc.). Remove only the number of panels absolutely necessary, and always employ the special lifting tools. Take care to return the panels to their original position.
Cleaning: wash with water and liquid detergents like a conventional floor. Hydrocleaners with a moderate jet of water can also be used.